Significant construction progress was achieved in April with in-ground issues mostly resolved and weather remaining fine. Work on the Main Building (MB) saw completion of footings and piers, and columns to the ground floor. Rapid progression of work also occurred on in situ walls, lift pit to ground floor and Main Switch Board pit. The platform and set out of the Support Precinct (SP) is complete and external works included considerable progress on storm water, chilled water runs, HV/comms runs and road sub grades.